Câu 17: ATM: Advanced Test Manager
Assume you are managing the system testing phase of a project. The system test execution period is scheduled to twenty weeks. All tests are manual tests. You are following a risk-driven test approach. During the last staff meeting the project manager tells you new deadlines that will not allow completion of all the sy…
Nội dung câu hỏi
Assume you are managing the system testing phase of a project. The system test execution period is scheduled to twenty weeks. All tests are manual tests. You are following a risk-driven test approach. During the last staff meeting the project manager tells you new deadlines that will not allow completion of all the system tests. Which of the following would you expect to be the best way to respond to this situation?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Prioritize executing the tests for the highest product risks and track these risks — đáp án hiện tại
- B. Remove testers from your test team, so that they can be assigned to other projects
- C. Automate all remaining tests
- D. No action is needed, test as much as possible in the remaining time period