Câu 4: ATM: Advanced Test Manager
You are estimating the effort for the integration testing activities of a new project. Consider the following factors, which can affect that estimation:I. Availability of re-usable test systems and documentation from previous, similar projectsII. Unexpected timing of components arrivalIII. Stability of the integration…
Nội dung câu hỏi
You are estimating the effort for the integration testing activities of a new project. Consider the following factors, which can affect that estimation:I. Availability of re-usable test systems and documentation from previous, similar projectsII. Unexpected timing of components arrivalIII. Stability of the integration test team (no turnover)IV. Many and geographically distributed sub-teamsWhich of the following statements is true?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. I. and II. can negatively affect the estimation III. and IV. usually favor the accuracy of the estimation effort
- B. II. and III. can negatively affect the estimation
- C. and IV. usually favor the accuracy of the estimation effort
- D. II. and IV. can negatively affect the estimation — đáp án hiện tại
- E. and III. usually favor the accuracy of the estimation effort
- F. III. and IV. can negatively affect the estimation
- G. and II. usually favor the accuracy of the estimation effort