Câu 5: CT-PT: Certified Tester Performance Testing
You are managing the testing efforts of an existing distributed system that manages inventories of automobile and light truck tires from multiple warehouses across the country. The system is being enhanced to track incoming restocking shipments at the point of entry to the warehouse and outbound sales shipments at the…
Nội dung câu hỏi
You are managing the testing efforts of an existing distributed system that manages inventories of automobile and light truck tires from multiple warehouses across the country. The system is being enhanced to track incoming restocking shipments at the point of entry to the warehouse and outbound sales shipments at the point of shipment from the warehouse, all of which are executed in real-time. System loads traditionally peak on Mondays due to built-up demand from the previous weekend. You are preparing a presentation to the business stakeholders, outlining your performance testing strategy. Which of the following is appropriate to present to this audience?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Established HTTP response per second goals that will have acceptable minimum, maximum, and average response times
- B. A test plan that includes specific technical specifications for the computing hardware to be used for performance testing
- C. A comprehensive list of support staff to be available during performance testing, including key members of the application development team
- D. The risks that may exist due to platform differences between the test environment and the production environment — đáp án hiện tại