Câu 18: CTFL-2018: ISTQB Certified Tester Foundation Level 2018
Tests have been specified for the latest software release and users have prioritised these.However, there are some dependencies between tests as shown in the table below (e.g. Test ID. ‘123’ cannot be run until Test ID. ‘456’ has been successfully completed). Which test execution schedule best meets the prioritisation…
Nội dung câu hỏi
Tests have been specified for the latest software release and users have prioritised these.However, there are some dependencies between tests as shown in the table below (e.g. Test ID. ‘123’ cannot be run until Test ID. ‘456’ has been successfully completed). Which test execution schedule best meets the prioritisation and dependency conditions?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. 5, 2, 3, 4, 1.
- B. 1, 5, 3, 1, 2.
- C. 1, 2, 3, 4, 5. — đáp án hiện tại
- D. 5, 1, 2, 3, 4.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.