You are working on calculating the estimation for a project. You have been given the following numbers by your manager, who is considered to be an expert in estimation:Optimistic = 35 days -Likely = 40 days -Pessimistic = 65 days -Apply the three-point estimation technique, what is the proper expression of the final e…

Nội dung câu hỏi

You are working on calculating the estimation for a project. You have been given the following numbers by your manager, who is considered to be an expert in estimation:Optimistic = 35 days -Likely = 40 days -Pessimistic = 65 days -Apply the three-point estimation technique, what is the proper expression of the final estimate?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. E is 46.3 days, SD = 35
  2. B. E is 40 days, SD = 6.67
  3. C. E is 37.3 days, SD = 43.3
  4. D. E is 43.3 days, SD = 5 — đáp án hiện tại