Câu 6: CTFL-V4-0: Certified Tester Foundation Level (CTFL) v4.0
You are working on calculating the estimation for a project. You have been given the following numbers by your manager, who is considered to be an expert in estimation:Optimistic = 35 days -Likely = 40 days -Pessimistic = 65 days -Apply the three-point estimation technique, what is the proper expression of the final e…
Nội dung câu hỏi
You are working on calculating the estimation for a project. You have been given the following numbers by your manager, who is considered to be an expert in estimation:Optimistic = 35 days -Likely = 40 days -Pessimistic = 65 days -Apply the three-point estimation technique, what is the proper expression of the final estimate?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. E is 46.3 days, SD = 35
- B. E is 40 days, SD = 6.67
- C. E is 37.3 days, SD = 43.3
- D. E is 43.3 days, SD = 5 — đáp án hiện tại
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.