Câu 7: ITIL 4 Practitioner Information Security Management
An organization has a small information security team. This team evaluates all changes to decide if there might be a security impact, and this evaluation is a significant bottleneck for the organization, resulting in delays that slow down the rate of business change. What should the organization do to manage this issu…
Nội dung câu hỏi
An organization has a small information security team. This team evaluates all changes to decide if there might be a security impact, and this evaluation is a significant bottleneck for the organization, resulting in delays that slow down the rate of business change. What should the organization do to manage this issue?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Allow staff from other teams to assess the security impact of changes that are frequent and low risk — đáp án hiện tại
- B. Communicate the importance of information security to stakeholders so that people understand the need for the delays
- C. Prioritize the evaluation of changes so that important business changes are not severely affected
- D. Automatically approve changes that have not been assessed within agreed times.