Câu 1: 70-348: Managing Projects and Portfolios with Microsoft PPM

You are a project manager for an organization that is using Microsoft Project. You have enabled Single Entry Mode and team members update their task using timesheets. You need to see how these updates impact your project before you approve the tasks. What should you do?

Nội dung câu hỏi

You are a project manager for an organization that is using Microsoft Project. You have enabled Single Entry Mode and team members update their task using timesheets. You need to see how these updates impact your project before you approve the tasks. What should you do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. From Project Professional Backstage view, review updates.
  2. B. From Project Professional Tracking Gantt, review updates.
  3. C. From Project Professional Task Usage, review updates.
  4. D. Go to the PWA Approvals page and run the rules you have configured. — đáp án hiện tại