CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 9: 70-348: Managing Projects and Portfolios with Microsoft PPM

Your organization is in the process of implementing Microsoft PPM. You need to configure Microsoft PPM to ensure that project managers can choose the tracking method for each of their projects. On the Task Settings and Display page, what should you do?

Nội dung câu hỏi

Your organization is in the process of implementing Microsoft PPM. You need to configure Microsoft PPM to ensure that project managers can choose the tracking method for each of their projects. On the Task Settings and Display page, what should you do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Set the tracking method to Free form. — đáp án hiện tại
  2. B. Select the check box Force project managers to use the progress reporting method specified above for all projects.
  3. C. Clear the check box Force project managers to use the progress reporting method specified above for all projects.
  4. D. Set the tracking method to Percent of work complete.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề