Câu 4: 70-348: Managing Projects and Portfolios with Microsoft PPM
This question requires that you evaluate the underlined text to determine if it is correct. Cost resources affect the schedule when theyre assigned to tasks. Review the underlined text. If it makes the statement correct, select "No change is needed". If the statement is incorrect, select the answer choice that makes t…
Nội dung câu hỏi
This question requires that you evaluate the underlined text to determine if it is correct. Cost resources affect the schedule when theyre assigned to tasks. Review the underlined text. If it makes the statement correct, select "No change is needed". If the statement is incorrect, select the answer choice that makes the statement correct.
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. No change is needed.
- B. Work resources. — đáp án hiện tại
- C. Material resources.
- D. Budget work resources.