Câu 15: 70-498: Delivering Continuous Value with Visual Studio 2012 Application Lifecycle Management
Your development team uses Scrum as its process framework. The business communicates a significant change in direction. The current sprint may become obsolete due to the changes. You need to determine whether the current sprint should be canceled. Under what circumstances should you cancel the current sprint?
Nội dung câu hỏi
Your development team uses Scrum as its process framework. The business communicates a significant change in direction. The current sprint may become obsolete due to the changes. You need to determine whether the current sprint should be canceled. Under what circumstances should you cancel the current sprint?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Team members are not able to complete the tasks that were committed to for the sprint.
- B. Major changes to have doubled the required time to complete the tasks.
- C. Impediments cause the tasks to not be completed within the sprint.
- D. The sprint goal becomes obsolete. — đáp án hiện tại