Câu 19: 70-498: Delivering Continuous Value with Visual Studio 2012 Application Lifecycle Management
A development team is attempting to use Scrum as its process framework. You join the team as the new scrum master. During a meeting, a developer states that his "task is done."You need to describe to the team how the word "done" relates to Scrum. What should you do?
Nội dung câu hỏi
A development team is attempting to use Scrum as its process framework. You join the team as the new scrum master. During a meeting, a developer states that his "task is done."You need to describe to the team how the word "done" relates to Scrum. What should you do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. The word "done" indicates that code has been approved for release to production.
- B. The word "done" indicates that code compiles and has been unit tested.
- C. The word "done" indicates that code has been approved through testing and quality assurance.
- D. The word "done" must be defined, communicated, and agreed to by the team. — đáp án hiện tại