CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 26: 70-498: Delivering Continuous Value with Visual Studio 2012 Application Lifecycle Management

Historically your IT group has done a poor job of reporting issues and successes to key decision makers in a timely manner, due to incomplete or inconsistent application lifecycle management (ALM) practices. You are implementing Scrum as the process framework for new projects. The scrum master will publish daily progr…

Nội dung câu hỏi

Historically your IT group has done a poor job of reporting issues and successes to key decision makers in a timely manner, due to incomplete or inconsistent application lifecycle management (ALM) practices. You are implementing Scrum as the process framework for new projects. The scrum master will publish daily progress reports to the product owner and key stakeholders. You need to view daily progress and identify if bottlenecks are occurring in the development process. Which report should you use?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Bug Trends
  2. B. Sprint Burndown
  3. C. Cumulative Flow — đáp án hiện tại
  4. D. Release Burndown

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề