Câu 16: 74-343: Managing Projects with Microsoft Project 2013
You are a project manager who uses Project Professional 2013. A senior stakeholder asks you to update your project to reflect your organization's scheduled two-week closure. You need to reflect the closure within your schedule. What should you do?
Nội dung câu hỏi
You are a project manager who uses Project Professional 2013. A senior stakeholder asks you to update your project to reflect your organization's scheduled two-week closure. You need to reflect the closure within your schedule. What should you do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Create a resource and specify non-working days for the resource which reflect the closure. Assign this resource to each task.
- B. Open the Project Calendar and modify the default work week by setting the dates as non-working time.
- C. Create a new calendar and assign this to the tasks that are scheduled over the period of closure.
- D. Open the Project Calendar and enter the planned closure in the Exceptions tab. — đáp án hiện tại