Câu 16: 74-343: Managing Projects with Microsoft Project 2013

You are a project manager who uses Project Professional 2013. A senior stakeholder asks you to update your project to reflect your organization's scheduled two-week closure. You need to reflect the closure within your schedule. What should you do?

Nội dung câu hỏi

You are a project manager who uses Project Professional 2013. A senior stakeholder asks you to update your project to reflect your organization's scheduled two-week closure. You need to reflect the closure within your schedule. What should you do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Create a resource and specify non-working days for the resource which reflect the closure. Assign this resource to each task.
  2. B. Open the Project Calendar and modify the default work week by setting the dates as non-working time.
  3. C. Create a new calendar and assign this to the tasks that are scheduled over the period of closure.
  4. D. Open the Project Calendar and enter the planned closure in the Exceptions tab. — đáp án hiện tại