You are managing a project by using Project Professional 2013. Your project schedule contains 1000 tasks which are in outline format. You discover that the Design summary task is located below the Build summary group of tasks. You need to move the Design summary task and its detail tasks to the proper location. What s…

Nội dung câu hỏi

You are managing a project by using Project Professional 2013. Your project schedule contains 1000 tasks which are in outline format. You discover that the Design summary task is located below the Build summary group of tasks. You need to move the Design summary task and its detail tasks to the proper location. What should you do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Click on the Design summary task name and drag it above the Build group of tasks.
  2. B. Make the Design summary task grouping a manual task, and drag the Design task name above the Build group of tasks.
  3. C. Cut all of the tasks below the Design summary task and paste them above the Build group of tasks.
  4. D. Click on the ID number for the Design summary task grouping and drag the group above the Build group of tasks. — đáp án hiện tại