Câu 9: 74-343: Managing Projects with Microsoft Project 2013

You are project manager who uses Project Professional 2013. Your organization uses Microsoft SharePoint 2013 and uses a SharePoint task list to define the tasks required on an upcoming project. The task list contains over100 items. You need to create a project based on the tasks in the SharePoint list in the most effi…

Nội dung câu hỏi

You are project manager who uses Project Professional 2013. Your organization uses Microsoft SharePoint 2013 and uses a SharePoint task list to define the tasks required on an upcoming project. The task list contains over100 items. You need to create a project based on the tasks in the SharePoint list in the most efficient manner. What should you do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Export the tasks into Microsoft Excel and then import the Excel file into Project Professional 2013.
  2. B. Edit the Project Summary Task hyperlink column to point to the SharePoint task list and click the Import button.
  3. C. Open the tasks directly from the SharePoint site into Project Professional 2013. — đáp án hiện tại
  4. D. Copy and paste the tasks from SharePoint into Project Professional 2013.