Câu 30: 74-343: Managing Projects with Microsoft Project 2013
You manage a project for an organization that uses Project Professional 2013. You reset the baseline for some selected tasks. After the baseline has been updated with the new values, you realize that some of the summary baseline duration values are not correct. You need to resolve this problem. What should you do?
Nội dung câu hỏi
You manage a project for an organization that uses Project Professional 2013. You reset the baseline for some selected tasks. After the baseline has been updated with the new values, you realize that some of the summary baseline duration values are not correct. You need to resolve this problem. What should you do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Update the summary tasks manually with the new duration values.
- B. Change all task durations to the same denomination values, such as days, weeks, or months.
- C. Reset the baseline for the selected tasks and select the Roll up baselines to all summary tasks option. — đáp án hiện tại
- D. Reset the summary tasks to manual scheduling.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.