Câu 18: 74-343: Managing Projects with Microsoft Project 2013

You are a project manager, and your organization uses Project Standard 2013. You have created a non-working day in a resource's calendar; however, the HR department notifies you that the resource will work that day after all. You need to reflect this change in the project in the most efficient manner. What should you…

Nội dung câu hỏi

You are a project manager, and your organization uses Project Standard 2013. You have created a non-working day in a resource's calendar; however, the HR department notifies you that the resource will work that day after all. You need to reflect this change in the project in the most efficient manner. What should you do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Open the Project calendar and mark the work day as working.
  2. B. Open the resource's working calendar and edit the Work Week details to set the day as working.
  3. C. Open the resource's working calendar and delete the exception. — đáp án hiện tại
  4. D. Open the resource's working calendar and mark the day as working.