Câu 27: 74-343: Managing Projects with Microsoft Project 2013
While creating a schedule with Project Professional 2013, you notice that there is a three-day duration on the Database Design task. After working for only two days, the resource performing the task reports two days of work and notifies you that the task is finished. You need to update the schedule with this informati…
Nội dung câu hỏi
While creating a schedule with Project Professional 2013, you notice that there is a three-day duration on the Database Design task. After working for only two days, the resource performing the task reports two days of work and notifies you that the task is finished. You need to update the schedule with this information. What should you do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Reschedule uncompleted work for the project schedule.
- B. Add two days of actual duration and change the remaining duration for the task to zero. — đáp án hiện tại
- C. Update the task to show 100% completion on the ribbon bar.
- D. Enter a status date for the task.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.