Câu 32: 74-343: Managing Projects with Microsoft Project 2013
Your company uses Project Professional 2013. You are building a schedule by using predecessors to help determine a logical duration. The following image shows a baselined list of tasks with predecessors: You have been told that Task C is optional, and you recommend inactivating the task to keep it visible on the sched…
Nội dung câu hỏi
Your company uses Project Professional 2013. You are building a schedule by using predecessors to help determine a logical duration. The following image shows a baselined list of tasks with predecessors: You have been told that Task C is optional, and you recommend inactivating the task to keep it visible on the schedule. You need to determine what the results are to the schedule when inactivating Task C. How should you answer?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. The finish date is reduced by four working days, cost remains unchanged, and baseline cost is reduced by $400.
- B. The finish date is reduced by five working days, cost remains unchanged, and baseline cost is unchanged.
- C. The finish date is reduced by six working days, cost is reduced by $400, and baseline cost is reduced by $400.
- D. The finish date is reduced by four calendar days, cost is reduced by $400, and baseline cost is reduced by $400.
- E. The finish date is reduced by six calendar days, cost is reduced by $400, and baseline cost is unchanged. — đáp án hiện tại