CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 32: 74-343: Managing Projects with Microsoft Project 2013

Your company uses Project Professional 2013. You are building a schedule by using predecessors to help determine a logical duration. The following image shows a baselined list of tasks with predecessors: You have been told that Task C is optional, and you recommend inactivating the task to keep it visible on the sched…

Nội dung câu hỏi

Your company uses Project Professional 2013. You are building a schedule by using predecessors to help determine a logical duration. The following image shows a baselined list of tasks with predecessors: You have been told that Task C is optional, and you recommend inactivating the task to keep it visible on the schedule. You need to determine what the results are to the schedule when inactivating Task C. How should you answer?

Minh họa câu hỏi

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. The finish date is reduced by four working days, cost remains unchanged, and baseline cost is reduced by $400.
  2. B. The finish date is reduced by five working days, cost remains unchanged, and baseline cost is unchanged.
  3. C. The finish date is reduced by six working days, cost is reduced by $400, and baseline cost is reduced by $400.
  4. D. The finish date is reduced by four calendar days, cost is reduced by $400, and baseline cost is reduced by $400.
  5. E. The finish date is reduced by six calendar days, cost is reduced by $400, and baseline cost is unchanged. — đáp án hiện tại

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề