Câu 36: AZ-801: Configuring Windows Server Hybrid Advanced Services
DRAG DROP -You have a server that runs Windows Server. You plan to back up the server to an Azure Recovery Services vault once per week starting on the next Saturday. You need to schedule the weekly backup and perform the initial backup as soon as possible. In which order should you perform the actions? To answer, mov…
Nội dung câu hỏi
DRAG DROP -You have a server that runs Windows Server. You plan to back up the server to an Azure Recovery Services vault once per week starting on the next Saturday. You need to schedule the weekly backup and perform the initial backup as soon as possible. In which order should you perform the actions? To answer, move all actions from the list of actions to the answer are and arrange them in the correct order. Select and Place:
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
-
A. Lựa chọn A bằng hình ảnh — đáp án hiện tại
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.