Câu 60: MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing

A customer produces light projection toys for holiday decorations throughout the year. You are in the first month of a season. Production flows take one day to complete. The floor supervisor reports that seasonal production targets will not be met. You review the Kanban schedule board and identify thousands of unplann…

Nội dung câu hỏi

A customer produces light projection toys for holiday decorations throughout the year. You are in the first month of a season. Production flows take one day to complete. The floor supervisor reports that seasonal production targets will not be met. You review the Kanban schedule board and identify thousands of unplanned jobs. You need to plan the jobs to be completed two weeks prior to the start of the next season. What are two possible ways to achieve this goal? Each correct answer presents a complete solution.NOTE: Each correct selection is worth one point.

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Set the Automatic planning option for each unscheduled job to Yes
  2. B. Manually schedule each unscheduled job on its due date — đáp án hiện tại
  3. C. Set the Automatic planning option for each unscheduled job to No
  4. D. Manually schedule each unscheduled job forward from the date of the end of the season — đáp án hiện tại
  5. E. Manually schedule each unscheduled job to the next period of the start of the next season