A company produces paints and assembles bicycle frames. You must account for paint drying time before assembly operations can begin. You need to set up the operation to encompass queue times. Which two options can you use? Each correct answer presents part of solution.NOTE: Each correct selection is worth one point.
Nội dung câu hỏi
A company produces paints and assembles bicycle frames. You must account for paint drying time before assembly operations can begin. You need to set up the operation to encompass queue times. Which two options can you use? Each correct answer presents part of solution.NOTE: Each correct selection is worth one point.
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Enter a value in the queue time after field for the painting operation — đáp án hiện tại
- B. Make a resource group for each size and color and assign that group to the operation
- C. Enter a value in the transit time on the painting operation
- D. Enter a value in the queue time before field for the assembly operation — đáp án hiện tại
- E. Build capabilities for each resource related to color