Câu 13: MB-330: Microsoft Dynamics 365 Supply Chain Management

A company creates several item costing versions. All new and existing items have costs associated with them. After defining the costs, the company notices the activation date has not been updated. You need to update the items to the current date for activation. What should you do?

Nội dung câu hỏi

A company creates several item costing versions. All new and existing items have costs associated with them. After defining the costs, the company notices the activation date has not been updated. You need to update the items to the current date for activation. What should you do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Set the item cost record status to Active — đáp án hiện tại
  2. B. Set the form date to today and leave the item cost record status at Pending
  3. C. Set the item cost record status to Pending
  4. D. Set the cost price and date of price on the released product