Câu 44: PL-400: Microsoft Power Platform Developer

HOTSPOT -You create a Power Platform solution to track purchasing requirements for bills of material (BOMs) and their subcomponents. The solution must meet the following requirements: ✑ Ensure that the BOMs are enabled to include the necessary subcomponents. ✑ Report changes to the BOMs or their sub-components that ar…

Nội dung câu hỏi

HOTSPOT -You create a Power Platform solution to track purchasing requirements for bills of material (BOMs) and their subcomponents. The solution must meet the following requirements: ✑ Ensure that the BOMs are enabled to include the necessary subcomponents. ✑ Report changes to the BOMs or their sub-components that are made by engineers. You need to configure the solution. What should you do to meet each requirement? To answer, select the appropriate options in the answer area.NOTE: Each correct selection is worth one point. Hot Area:

Minh họa câu hỏi

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Lựa chọn A bằng hình ảnh — đáp án hiện tạiLựa chọn A
Giải thích

https://docs.microsoft.com/en-us/powerapps/developer/data-platform/use-change-tracking-synchronize-data-external-systems