Câu 28: NS0-184: NetApp Certified Storage Installation Engineer, ONTAP

You have added two new AFF A250 nodes to an existing 4-node cluster with NetApp CN1610 cluster network switches. Although the nodes can join the cluster, the storage failover show command output shows that the NVRAM log is not synchronized, and it cannot reach the partner over an HA interconnect. In this scenario, whi…

Nội dung câu hỏi

You have added two new AFF A250 nodes to an existing 4-node cluster with NetApp CN1610 cluster network switches. Although the nodes can join the cluster, the storage failover show command output shows that the NVRAM log is not synchronized, and it cannot reach the partner over an HA interconnect. In this scenario, which two statements are true? (Choose two.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. The AFF A250 requires switches with 40GbE port support.
  2. B. The AFF A250 uses different ports for the cluster and the HA interconnect.
  3. C. The AFF A250 requires switches with 25GbE port support. — đáp án hiện tại
  4. D. The AFF A250 uses the same port for the cluster and the HA interconnect. — đáp án hiện tại