Câu 6: NCS-CORE-6-8: Nutanix Certified Services - Core (NCS-Core) 6.8

During a Site Readiness Check, a customer informed the consultant that there is no NTP server currently configured in the environment. Which two statements should the consultant consider for continuing the cluster deployment? (Choose two.)

Nội dung câu hỏi

During a Site Readiness Check, a customer informed the consultant that there is no NTP server currently configured in the environment. Which two statements should the consultant consider for continuing the cluster deployment? (Choose two.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. An NTP server is not required for cluster Foundation and can be added later.
  2. B. At least one external NTP server must be used to complete Foundation process. — đáp án hiện tại
  3. C. At least 3 NTP servers must be provided in a comma-separated list.
  4. D. If an NTP server is provided using FQDN, a DNS server is required. — đáp án hiện tại