Which tasks should a project manager perform in order to manage the project schedule effectively?
Nội dung câu hỏi
Which tasks should a project manager perform in order to manage the project schedule effectively?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities, Develop Schedule
- B. Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule, Control Schedule — đáp án hiện tại
- C. Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Durations, Estimate Cost of Activities, Develop Schedule
- D. Define Activities, Sequence Activities, Estimate Activity Durations, Define Quality of Activities, Estimate Cost of Activities, Develop Schedule