Câu 139: Certified Associate in Project Management (PMI-100)

In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?

Nội dung câu hỏi

In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Hold a face-to-face meeting with the project manager and warn them
  2. B. Point the director to a link where they can take a look at the reports
  3. C. Invite stakeholders to attend monthly progress review meetings — đáp án hiện tại
  4. D. Ask the project manager to update the monthly status report distribution list