Câu 139: Certified Associate in Project Management (PMI-100)
In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?
Nội dung câu hỏi
In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Hold a face-to-face meeting with the project manager and warn them
- B. Point the director to a link where they can take a look at the reports
- C. Invite stakeholders to attend monthly progress review meetings — đáp án hiện tại
- D. Ask the project manager to update the monthly status report distribution list