Câu 48: Certified Associate in Project Management (PMI-100)
Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?
Nội dung câu hỏi
Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Defining, sequencing, estimating activity durations, and developing a schedule model are so tightly linked that they are viewed as a single process.
- B. The detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge.
- C. An iterative scheduling and on-demand, pull-based scheduling will be required. — đáp án hiện tại
- D. To address the full delivery schedule, a range of techniques may be needed and then need to be adapted.