Câu 109: Certified Associate in Project Management (PMI-100)

A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job. What kind of relationship between the tasks impacted the painting work?

Nội dung câu hỏi

A construction project is underway, and during the progress review the painter complained that the task could not be started because the mason has not finished the plastering job. What kind of relationship between the tasks impacted the painting work?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Finish-to-Finish (FF)
  2. B. Start-to-Finish (SF)
  3. C. Finish-to-Start (FS) — đáp án hiện tại
  4. D. Start-to-Start (SS)