CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 66: Certified Associate in Project Management (PMI-100)

A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?

Nội dung câu hỏi

A project manager is analyzing a few network diagrams in order to determine the minimum duration of a project. Which diagram should the project manager reference?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. A diagram in which resource optimization has been applied.
  2. B. A diagram in which the critical path method has been applied. — đáp án hiện tại
  3. C. A diagram in which a predefined series of activities has been organized.
  4. D. A diagram which shows a combination of resource and time optimization.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề