Câu 63: Certified Associate in Project Management (PMI-100)

A stakeholder is reading project documents given by the project manager. The stakeholder is curious about the difference between a verified deliverable and an accepted deliverable. Which of the following definitions can the project manager use to explain the difference?

Nội dung câu hỏi

A stakeholder is reading project documents given by the project manager. The stakeholder is curious about the difference between a verified deliverable and an accepted deliverable. Which of the following definitions can the project manager use to explain the difference?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. An accepted deliverable is approved by the project team; a verified deliverable is approved and formally signed off by the customer or sponsor.
  2. B. An accepted deliverable has been checked and confirmed for accuracy through the Control Quality process; a verified deliverable meets acceptance criteria that is formally signed off and approved by the customer or sponsor.
  3. C. An accepted deliverable meets acceptance criteria and is formally signed off and approved by the customer or sponsor a verified deliverable is a completed project deliverable that has been checked and confirmed for accuracy through the Control Quality process. — đáp án hiện tại
  4. D. An accepted deliverable meets acceptance criteria and is signed off by the project manager; a verified deliverable meets acceptance criteria and is signed off by the customer or sponsor.