Câu 11: Certified Associate in Project Management (PMI-100)

Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties in order to temporarily or partially resolve the problem. Which technique should the project manager use?

Nội dung câu hỏi

Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties in order to temporarily or partially resolve the problem. Which technique should the project manager use?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Withdraw/Avoid
  2. B. Smooth/Accommodate
  3. C. Compromise/Reconcile — đáp án hiện tại
  4. D. Collaborate/Problem Solve