Câu 62: CPMAI: Cognitive project management in AI
During CPMAI Phase II of your project, your team is going through their data collection needs. One team member wants to make use of pre-trained models while another member is adamantly against it. As the project lead, what should you do?
Nội dung câu hỏi
During CPMAI Phase II of your project, your team is going through their data collection needs. One team member wants to make use of pre-trained models while another member is adamantly against it. As the project lead, what should you do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Evaluate your data and use only what you have and build all models in house.
- B. Evaluate your data and see if using pre-trained models make sense. If so, have the team see what pre-trained models your company already owns and use those
- C. Evaluate your data and see if using pre-trained models make sense. If so, have the team do research to find the ones that best suit your project. — đáp án hiện tại
- D. Have one team build all models in-house and the other team use pre-trained models and see which team’s models perform better.