Câu 79: CPMAI: Cognitive project management in AI
A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project manager for a rough estimate of the project duration. Based on her experience with three similar projects, the project manager provides an estimate of 8-10 months.What’s w…
Nội dung câu hỏi
A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project manager for a rough estimate of the project duration. Based on her experience with three similar projects, the project manager provides an estimate of 8-10 months.What’s wrong with this timeframe?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. It’s underestimating the project timeline by 3 months
- B. It fits into a waterfall timeframe, but not an agile project timeframe
- C. It’s not accounting for data preparation timelines — đáp án hiện tại
- D. It’s not accounting for potential project delays