Câu 1: DASSM: Disciplined Agile Senior Scrum Master

In the last few iterations/sprints, the velocity has dropped due to poor communication between team members, resulting from team size and geographical distribution. Which two actions could the team take to improve performance? (Choose two.)

Nội dung câu hỏi

In the last few iterations/sprints, the velocity has dropped due to poor communication between team members, resulting from team size and geographical distribution. Which two actions could the team take to improve performance? (Choose two.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ask management to offer bonuses to high performing developers.
  2. B. Introduce a new, more effective collaboration tool for remote workers. — đáp án hiện tại
  3. C. Ask management to provide a larger space to colocate the team.
  4. D. Split the team in smaller teams working on different product backlogs.
  5. E. Split the team into smaller teams working on the same product backlog. — đáp án hiện tại