Câu 5: PfMP: Portfolio Management Professional
A large organization has an extensive portfolio. However, senior management is concerned that these efforts may not be completely aligned with previously agreed upon portfolio metrics, and they have expressed this concern to the portfolio management team. The team’s response should be to:
Nội dung câu hỏi
A large organization has an extensive portfolio. However, senior management is concerned that these efforts may not be completely aligned with previously agreed upon portfolio metrics, and they have expressed this concern to the portfolio management team. The team’s response should be to:
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. revise the metrics to be collected from the various components and meet with the component managers to explain the resulting new processes. — đáp án hiện tại
- B. hold performance reviews with the managers of the active portfolio components to elicit reportable information on their status and progress.
- C. ensure at the next steering committee meeting that senior management is fully aware of all of the information already available to them.
- D. review the established performance measures with senior management to ensure that the metrics are providing the information that they require.