Câu 160: PgMP: Program Management Professional
What actions are taken in the process of developing and maintaining a program risk register?
Nội dung câu hỏi
What actions are taken in the process of developing and maintaining a program risk register?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and provide the foundation for the risk management plan.
- B. Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and identify the root cause of potential risks. — đáp án hiện tại
- C. Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and proactively manage program issues.
- D. Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and identify residual risks.