Câu 63: PgMP: Program Management Professional
A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of US$1 million. Since the shutdown was not anticipated, what should the program manager do first?
Nội dung câu hỏi
A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of US$1 million. Since the shutdown was not anticipated, what should the program manager do first?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Implement the appropriate risk response plan and inform the stakeholders of the planned actions.
- B. Utilize contingency reserves to hire contractors, which will accelerate the schedule to meet the original milestone.
- C. Evaluate the impact, reassess the program risk, and determine options to be presented to the governance board. — đáp án hiện tại
- D. Collaborate with the sponsor to determine options and negotiate a new date for the milestone.