You are the program manager for your organization and management has asked you to be certain to finalize the lessons learned documentation for your program. When will the lessons learned documentation be created?

Nội dung câu hỏi

You are the program manager for your organization and management has asked you to be certain to finalize the lessons learned documentation for your program. When will the lessons learned documentation be created?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Lessons learned are in program execution.
  2. B. Lessons learned are created at each program deliverable.
  3. C. Lessons learned are created during the program closure. — đáp án hiện tại
  4. D. Lessons learned are created during the program archive.