Câu 27: PgMP: Program Management Professional
After taking over a program, a program manager reviews the program's status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs. The program manager establishes earned value (EV) metrics and determines that the program has a budget of US$2.1 million, is three mon…
Nội dung câu hỏi
After taking over a program, a program manager reviews the program's status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs. The program manager establishes earned value (EV) metrics and determines that the program has a budget of US$2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000. Based on this information, the program manager determines which of the following?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. The schedule is US$30,000 under budget — đáp án hiện tại
- B. The cost is US$20,000 under budget
- C. The schedule is US$10,000 over budget
- D. The cost is US$20,000 over budget