Câu 80: PgMP: Program Management Professional

The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan, determines that project A can wait until the resource becomes available, and assigns the resource…

Nội dung câu hỏi

The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan, determines that project A can wait until the resource becomes available, and assigns the resource to project B. This is an example of which of the following?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Program resource management planning
  2. B. Program risk mitigation
  3. C. Resource interdependency management — đáp án hiện tại
  4. D. Project resource planning