Câu 144: PgMP: Program Management Professional

You are the program manager for your organization. You and your program team have been creating and transferring the program benefits to operations as feasible in your program execution. The process of delivering the program's benefits describes what process in program management?

Nội dung câu hỏi

You are the program manager for your organization. You and your program team have been creating and transferring the program benefits to operations as feasible in your program execution. The process of delivering the program's benefits describes what process in program management?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Quality control
  2. B. Benefits management — đáp án hiện tại
  3. C. Direct and manage program execution
  4. D. Quality assurance