Câu 50: PgMP: Program Management Professional

A company is releasing a new product geared toward a specific geographic area. The program manager has received the program objectives and developed the program roadmap, which consists of six program components. Approval from the program governance board has been obtained. What is the program manager's next step?

Nội dung câu hỏi

A company is releasing a new product geared toward a specific geographic area. The program manager has received the program objectives and developed the program roadmap, which consists of six program components. Approval from the program governance board has been obtained. What is the program manager's next step?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Assign project managers and resources
  2. B. Classify the program's benefits
  3. C. Identify the program sponsor and program stakeholders — đáp án hiện tại
  4. D. Develop the program business case