Câu 5: PgMP: Program Management Professional
A program completes all component projects and all identified benefits are being delivered. However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters. To ensure the realization of long-term benefits, what should the program manager use?
Nội dung câu hỏi
A program completes all component projects and all identified benefits are being delivered. However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters. To ensure the realization of long-term benefits, what should the program manager use?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Benefits register
- B. Benefits sustainment plan — đáp án hiện tại
- C. Benefits management plan
- D. Benefits transition plan