Câu 5: PgMP: Program Management Professional

A program completes all component projects and all identified benefits are being delivered. However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters. To ensure the realization of long-term benefits, what should the program manager use?

Nội dung câu hỏi

A program completes all component projects and all identified benefits are being delivered. However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters. To ensure the realization of long-term benefits, what should the program manager use?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Benefits register
  2. B. Benefits sustainment plan — đáp án hiện tại
  3. C. Benefits management plan
  4. D. Benefits transition plan