Câu 150: PgMP: Program Management Professional
A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list. During the final review of the RFPs, the program manager is informed that the new bidder is a relative of the project manager. Although the bid meets all company…
Nội dung câu hỏi
A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list. During the final review of the RFPs, the program manager is informed that the new bidder is a relative of the project manager. Although the bid meets all company policies, the program manager is concerned about a conflict of interest. What should the program manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Select the best bid from the prequalified vendor list.
- B. Accept the bid from the new vendor and document the decision.
- C. Advise the sponsor of a possible conflict of interest prior to awarding the bid. — đáp án hiện tại
- D. Add the new vendor to the prequalified list and replace the project manager.