Câu 182: PgMP: Program Management Professional
Robert is the program manager for his organization which operates in a matrix structure. Resources in Robert's program will be utilized on several projects in and out of his program. He wants to be certain that all of the resources will be planned accordingly and that the project managers communicate with one another…
Nội dung câu hỏi
Robert is the program manager for his organization which operates in a matrix structure. Resources in Robert's program will be utilized on several projects in and out of his program. He wants to be certain that all of the resources will be planned accordingly and that the project managers communicate with one another about when the resources will be needed and utilized in the projects. What plan shouldRobert create along with the project managers to ensure that the resources are scheduled and managed effectively?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Resource management plan — đáp án hiện tại
- B. Program management calendar
- C. Schedule management plan
- D. Resource calendar