Câu 134: PgMP: Program Management Professional
After attending a technology exposition, an influential stakeholder believes that integrating a new technology into the program will increase benefits and help shorten the schedule. The stakeholder asks the program manager to immediately include the new technology into the program. What should the program manager do n…
Nội dung câu hỏi
After attending a technology exposition, an influential stakeholder believes that integrating a new technology into the program will increase benefits and help shorten the schedule. The stakeholder asks the program manager to immediately include the new technology into the program. What should the program manager do next?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Assess the new technology and discuss the results with the program steering committee to determine next steps.
- B. Start the change management process and submit a change request to integrate the new technology.
- C. Inform the stakeholder that the program will not be changed until proof of concept (PoC) is completed. — đáp án hiện tại
- D. Research the new technology and begin its integration during the next development cycle.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.