CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 214: PgMP: Program Management Professional

The chief executive officer (CEO) informs the program manager that the delivery date for project A must be compressed by two months to accommodate market needs. Project A relies upon deliverables from projects B and C. Which of the following should the program manager do first?

Nội dung câu hỏi

The chief executive officer (CEO) informs the program manager that the delivery date for project A must be compressed by two months to accommodate market needs. Project A relies upon deliverables from projects B and C. Which of the following should the program manager do first?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Direct the three project managers to crash their projects, to allow project A the two months of scheduling needed.
  2. B. Review the program resource management plan with the three project managers emphasizing their critical paths and shared critical resources to understand the possibility of accelerating the schedule. — đáp án hiện tại
  3. C. Convene the change board to evaluate the cost/benefit of the compression and the impact on the overall program.
  4. D. Engage the executive sponsor and program board to evaluate the CEO's request and determine if the project manager should act on it.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề