Câu 110: PgMP: Program Management Professional
A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?
Nội dung câu hỏi
A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. .93 — đáp án hiện tại
- B. .82
- C. $323,889
- D. -$38,889
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.